By hafeezrm


For over three decades, I worked for a development bank. My main job was to evaluate proposals for setting up of industrial projects initially as an Officer and later as Head of the Division. I have many interesting stories to share in project planning and implementation. One such story is the success of Pakistan Mineral Water Corporation (PMWC) in water-bottling. The company no more exists. It has since been swallowed up by multinational brands of bottled-water like AVA, Aquafina & Culligan.

In early 1986, three companies, including PMWC, applied for water- bottling plants. The market justified only one. I called sponsors of the companies and told them that I would recommend the case of one which could demonstrate its ability to go into production before October 1987. “What is that for!!!” all spoke at the same time. “Well, as a bottlers you should know upcoming Cricket Cup at Karachi” I told them and added, “Anyone who catches the event would have an instant success.” Only one, J. Rashid of PMWC, turned up with a rudimentary sketch of CPM which convinced me of his ability to beat the deadline.


WHAT IS CPM?

Simply put, CPM stands for Critical Path Method used in planning and controlling time. It helps estimate time for project completion, pin-points activities critical for achieving the target. Above all, it gives a graphic view of the activities of a project which is easy to understand in one go.


BACKGROUND INFORMATION

As per information provided by J. Rashid, the project required basic facilities like land, building and machinery which have been shown in Table #1 along with estimated time. As would be observed that after acquiring land, the company can go for three activities: (i) placing order for machinery, (ii) construction of building, (iii) placing order for plastic bottles for water filling.

When buildings are complete, machines can installed and the same time, racks can be erected for storing plastic bottles. Thus the company can go for trials runs as necessary pre-requisites are in order.


Format of a network or CPM varies. Basic structure is given in the text books or Software (MS Project 2007) which can be suitably modified. Personally, I like a detailed format for presentation.

Here each box or node has nine cells as shown in its legend. ES means Early Start while EF mean Early Finish.

In sketch # 1, some information has already been inserted about a particular activity such as ID, Description & Duration. The activities are also placed keeping their relationships in view.

Sketch # 1

FORWARD PASS

Let us start with ES & EF. This is simple except where we confront a Merge Event. We would insert Zero ( or expected date ) in the first cell of activity #1. Since duration for this activity is 1 month, the EF would be 0 + 1 = 1. Same would be carried for activities #2, #3 & #4 and EF worked out accordingly.

The ES of activity #5 would be 9, same as EF of its predecessor #3. It is natural; you cannot start erecting racks (#5) unless buildings (#3) are complete.

When you go next to activity #6, you would see two activities (#2 & #3) are merging. Obviously, you cannot start installation of machines (#6) unless the machinery has arrived as per order (#2) and buildings (#3) are complete. Here we would take maximum of EF of the both as both must be complete before #6 can be started. In the same way, we can complete rest of the diagram. We find that the project would take 19 months to be completed as shown in Sketch # 2 below:

Sketch #2

BACKWARD PASS

As the name implies, we move backward to the origin. In this example, the project completion time is 19 months. So its Early Finish (EF) or Late Finish (LF) must be the same. In other words, call it early or late, it must be finished by 19th month.

We start from last activity #8 and insert 19 in its LF cell. This activity has duration of 4 monthss. Calculating backward, we find that its LS should be 15th months (19 - 4 =15 ). In other, if #8 was started as late as on 15th months and it takes 4 months, it could still meet the deadline of 19 months.

We go back further and trace tails of any arrows touching #8. We find two, one linking with #7 (Store Raw Materials) and other with #6 (install machinery). We would put 15 in the LF Cells of #6 & #7. We can now calculate their LS by deducting from 15 their respective durations. For example, the LS of #6 should now be 9 (15-6=9).

We can continue likewise till we hit a "Burst Event" like #3 & #1. For explanation, #1 would be better as three activities are leading back to this activity. (There are three tails touching #1.) In such a situation, we shall take minimum of the LS of the three which is one month and it would be LF of #1. Why? The longest activity after #1 is #3. In order to enable #3 to start on time, it is essential that the preceding activity is completed well in time.

The complete working is shown in Sketch # 3 below:

Sketch # 3


WHAT IS A PERT?

PERT stands for “Project Evaluation and Review Technique”. It is almost the same as CPM except for the following differences:

  • CPM is for repeated projects while PERT is for first-timers.
  • CPM is used both for time and cost whereas in PERT only time is taken care of.
  • Because CPM is for repeated projects, there is a track-record or database of previous projects. It enables the manager to be realistic in their estimates. For PERT, being for first time projects, one has to ask the knowledgeable persons to give time-estimates for each activity as to (i)Minimum time as in most favorable conditions, (ii) Maximum time as in most unfavorable conditions and (iii) Normal time. Thereafter a weighted average is calculated as shown in Sketch #4.

 

Sketch #4


OTHER ISSUES

Once time has been estimated, the rest is the same as in CPM.

In the upcoming articles, I would cover probabilities of project completion in different situations, relationship amongst activities, slacks and resource management.

Comments

RSS for comments on this Hub

usman alvi  says:
8 months ago

sir u explain CPM and PERT tromendasly i have little confusion in backward pass of CPM i need little guidence of ur expertise for my clearification.

asifkamran  says:
8 months ago

nice case

shahnawaz sheikh profile image

shahnawaz sheikh  says:
8 months ago

sir thank you for the intresting artical

i fully ubderstand the CPM part but have a little confusion in understanding the Pert specially the diagram , some more explanation would help .

thank you again

hafeezrm profile image

hafeezrm  says:
8 months ago

Thanks for your comments. As the name implies, we move backward to the origin. In this example, the project could be completed in 19 days as proved in the forward pass. This is the shortest time for completion. (Critical Path is longest path but shows shortest time for completion. Other paths are of lesser duration. For example, if you go from Activity #1 to Activity #4 to #7 and finally #8, the total duration would be 10 days or much lesser than 19 days.

So the project's EF (Early Finish) and LF(Late Finish) must be the same. From there we go back to the tails of arrows which, in one case, touches #7. We put LS of #8 in LF of #7. Another tail points towards #6. It should have the same property in LF i.e. 15. The problem would come when there are two or more tails. For example, if you see #3, it has backward link with #5 & #6. We would take lower of the two. Incidentally, both have the same property i.e. 9. We go further back to Activity #1 where three tails are touching. Lowest of the three would be carrid back to #1 ( others are 10 & 4 for activity #2 &4 ). Obviously, finishing #1 latest by day 1 would enable all the successors(#2, #3 & #4) to start well in time. The benefit would mainly go to Activity # 3 which cannot be delayed. Others might have some margin for delay which, as I said earlier, would be covered in my next article.

Hope this clarifies the position. If not, please do not hesitate to ask.

hafeezrm profile image

hafeezrm  says:
8 months ago

For Mr. Shahnawaz Sheikh.

In CPM & PERT, there is a small difference in working and that too only in the initial stage. While for PERT, we use a weighted average of minimum, maximum and most likely, in CPM we are already given a completion time and so there is no need to compute. In PERT, we use the formula: (minimum x 1)+(maximum x 1)+( most likely x 4). The total would be divided by 6 since weights are six (1+1+4) to arrive at Time Estimate.

Hope this clarifies you query?

khalid akhter  says:
8 months ago

Its a realy very nice xplanation of PERT n CPM..i learned a lot for this practical xample as i have already learn these 2 mthod in ICMA ...but u desribed it very well ..nice case stdy

Fahad Khan  says:
8 months ago

Sir, thank you so much for sharing this article. It really helped me in understanding the topic in an easy way.

shahnaz otho  says:
8 months ago

Sir i thank you for giving us detailed view of CPM and PERT but still there is a little confusion in understanding Sketch #3. However the casestudy is flawless. Thank you

Emran Ali profile image

Emran Ali  says:
8 months ago

Respected Sir ,

Thanks for sending this case study , it has certainly cleared my mind .

Yours sincerely

Imran Ali

hafeezrm profile image

hafeezrm  says:
8 months ago

For Shahnawaz Otho. Please read my comments, third from the top. It further explains the nature of sketch #3.

MUHAMMAD DANIAL  says:
8 months ago

THANK YOU SIR FOR THIS A VERY INTRESTING CASE.

THIS CASE GIVE GREAT KNOWLEDGE ABOUT CPM AND PERT. IT IS VERY HELPFUL FOR ME IN MY FUTURE LIFE.

THANK YOU SIR ONCE AGAIN.

Mushtaq Ahmed  says:
8 months ago

Great practical example on cpm and pert.

Ms project is wonderfull tool to work with. i use ms project for project managment at my job as design and development head at Allied Engineering . I have video training available for learning ms project . this training is step by step and easy to follow.

Regards,

Mushtaq Ahmed

MBA-4 Bahria University

Malik Tahir  says:
8 months ago

Thank You very much for sharing such a knowledgeable case.

I will ask you for help later on.........

Uptil now, each and every aspects of case, are clear.

Adeel Aleem 4B.  says:
8 months ago

This case study contains vivid explanation in every aspect; hence i firmly understood the nature, criteria and practical exposure of PERT & CPM.

Cognizance case study.. good job done... Thanks.

linjingjing profile image

linjingjing  says:
8 months ago

Good article

25724

Qamar Bezanjo  says:
8 months ago

Sir we student of MBA4 of Bahria University are very much thankful to you for giving such information through mails also, as we are already given good lectures by you in class but placing such articles on net and mailing students clears the mind of students all around .... as i had a confusion in backward pass but through your above comment i understood that .... Hope we will have such type of good articles in our whole semester....

Thankyou

Regards,

Qamar Bezanjo

MUHAMMAD AUSAF MBA-4A(BU)  says:
8 months ago

sir thank you for the intresting artical

i have a little confusion in understanding the FORWARD PASS specially the diagram , some more explanation would help .

thank you again

SANA GHAYOOR MBA-4A  says:
8 months ago

Sir, thank you so much for sharing this article. It really helped me in understanding the topic in an easy way.

ABDUL AZIZ MBA_4A  says:
8 months ago

Respected Sir ,

Thanks for sending this case study.

Yours sincerely

ABDUL AZIZ

Shahnaz otho  says:
8 months ago

thank you Sir.

sheraz khan(MBA-4A)  says:
8 months ago

SIR,I THANKS TO YOU FOR THIS WONDERFUL AND INTERESTING CASE STUDY.IT HELPS IN INCREASING OF KNOWLEDGE.SIR I HAVE LITTLE CONFUSION ON THE PART OF FORWARD PASS,

Numan Nazir  says:
8 months ago

Thank you v. much.....

Am I rite if i interpret sketch # 3 as:

If the company starts late....It is Intalling racks, machinery and packing orders at the same time. Must start pacing orders by the 11th month and must finish it by the end of the 13th month....Must start install Machinery in Month 9.....and the company is instaaling machinery and packing orders in month # 11....

Kashan Pirzada MBA (4A) (BU)  says:
8 months ago

Thank you sir for sending this article , This article is really clear the concept of CPM , PERT, FP and BP which you are trying to deliver.

Remember me in your prayers!

Kashan Pirzada MBA (4A) (BU)  says:
8 months ago

Thank you sir for sending this article , This article is really clear the concept of CPM , PERT, FP and BP which you are trying to deliver.

Remember me in your prayers!

sanam khan  says:
8 months ago

sir

thanq for sharing this article.

samreen habib MBA-4A  says:
8 months ago

AASALAM-0-ALAYKUM SIR..

THANKS FOR SENDING ME SUCH AN INFORMATIVE ARTICLE...ITS REALLY VERY GOOD..BUT I HAVE LITTLE BIT CONFUSION REGARDING DIAGRAMS..

mubin_ashraf profile image

mubin_ashraf  says:
8 months ago

Thats really informative

I think that these pictorial views give me more understanding to have in your articles.

Regards,

Mubin Ashraf.

Asif Kamran  says:
8 months ago

thank yo so much for sharing your articale

Fahad_Khan profile image

Fahad_Khan  says:
8 months ago

I've saved this case study for future reference. Thanks a lot to Mr. Hafeez Ur Rehman for this excellent work.Regards,Muhammad Fahad Khan.

munazza farheen mba 4a  says:
8 months ago

thank you sir for sharing with us such a valueable article.The article has was worth reading and increased my knowledge.

farhan hussain MBA-4A  says:
8 months ago

THIS ARTICLE IS VERY MUCH WORTH FULL AND I AM GLAD THAT YOU SHARED IT WITH US. THANK YOU SIR.

ASAD SHERAZ MBA-4B  says:
8 months ago

This aricle is very informative thank you so much about sharing of information

sufyan majeed  says:
8 months ago

very informative artical

muhammad saleem MBA 4(A) Morning  says:
8 months ago

thank you sir for giving such a knowledgeable article that assisted to insrease me information about pert & cpm......

osama  says:
7 months ago

why the most likely to happen take the weight 4

hafeezrm profile image

hafeezrm  says:
7 months ago

It is a normal condition others ( minimum or maximum, optimistic or pessimistic, most favourable or un-favourable) have less chances. Considering law of probability normal condition is likely to occur many times in a given scenario and therefore given the weight of 4. By normal condition mean usual condition. If there are power outage for 4 hours a day, it is said to be normal or most likely. If condition improve for an extended period of time to no-power outages, it would become normal.

osama  says:
7 months ago

thanks for your care ,but iam asking why specialy 4 not 3 or 5 (i need an explanation from the point of statistical view)

hafeezrm profile image

hafeezrm  says:
7 months ago

PERT Formula for Variance is developed after long deliberations by the statisticians. They have given a weight of four to most-likely event. (Certainly, this weightage is not mine).

astray555  says:
7 months ago

Thank you very much for this hub! It's really very useful.. I appreciate it very much and will follow your advice!

kamran  says:
6 weeks ago

hi sir it was very informative and here one thing i would like to say that your reaction to where student is not confortable is very good.whatever problem we discuss more in cless you send related material on it.thanks sir

Rufi Shahzada profile image

Rufi Shahzada  says:
6 weeks ago

Dear Sir,

You have explained CPM and PERT so well, the sketches were so simple and easy. Amazing work!

You bring each and every thing to single platform. After reading this HUB, I ain't need to open book and brush up again.

A MILLION THANKS!

RUFI SHAHZADA

haris saleem  says:
6 weeks ago

now very much clear sir :)

TEERATHMAHESHWARI profile image

TEERATHMAHESHWARI  says:
6 weeks ago

dear sir;

Before i read your this artical i have read abot PERT and CPM in Operational Mnagement book of Jay hiezer and Barry render but they were more difficult to understand but as i read yor artical i all my concept regarding CPM , PERT, AND CRITICAL PATH has been cleared.

Thanks for your explaination of above artical in simple and understansable way.

maria javed  says:
6 weeks ago

Dear sir,

after going through the article i really come to understand the real essences of PERT & CPM i have studied this topic before but the book reading was not that much easy as you just explained it in a very simple way.now my concepts are more clear and these diagrams are really helpfull to understand the whole structure but sir its really time consuming to build up the boxes as we do not get that much time in the examination,i hope so you will surely come up with some smart tricks in the lecture to resolve this problem.

all over its really worth full for of us

thanks a lot for sharing this information with us

Asma Shabbir  says:
6 weeks ago

Asalam o Alikum Sir

Thanx for sharing this valuable information with us

Sir can you explain why we use pert if cpm give us both time and cost estimate for a project??

hafeezrm profile image

hafeezrm  says:
6 weeks ago

CPM is used for repeated projects. It is based on track record or database already with us. But when we want to venture into some projects which we have never handled before, we are bound to use PERT where we ask knowledgeable persons to give us optimistic, pressimistic and normal time estimates. By taking their weighted average, we can have an idea about expected duration.

Syed Kabeer Ehsan profile image

Syed Kabeer Ehsan  says:
6 weeks ago

Dear Teacher,

Thanque for sharing this article, it helps alot to understand your class lectures...

amirah  says:
5 weeks ago

Thank you Sir! very informative and well explain

Mehwish Saleem  says:
5 weeks ago

ASlam alekum sir,

i tried my level best to understand the pert and cpm concept but that didnt work, but through this article i tried this example at home and got the answer.Thank you so much sir.

Kevin Peter profile image

Kevin Peter  says:
2 weeks ago

Hi ,This is very helpful for me in writing my MBA assignment.. You explained complicated mathematical model in a simplified way

hafeezrm profile image

hafeezrm  says:
2 weeks ago

Thanks Kevin Peter for your comments. I am MBA myself. I did it in 1965 from IBA Karachi, Pakistan which was affiliated with University of Southern California. I joined PICIC, an affiliate of the World Bank which offered me a scholarship to go for a diploma to Harvard Business School in Project Evalaution. This honed my skills.

shehazad3d profile image

shehazad3d  says:
2 weeks ago

hi every body,

i am architecrural graphic designer freelancing working or job live in karachi , engineering architectural, structures and interior exterior views drawing done very perfectaly please contect me and see my some work on net www.flickr.com/shehazad 0321-2152122

neha  says:
7 days ago

thanks sir..

really this helped me alot in preparing my seminar over cpm and cleared my concepts too.

tanu  says:
7 days ago

really this text helped me alot

and cleared my doubts..

thanks .

Submit a Comment

Members and Guests

Sign in or sign up and post using a hubpages account.


optional


  • No HTML is allowed in comments, but URLs will be hyperlinked
  • Comments are not for promoting your hubs or other sites

working